Last updated 21 April 2020.

We are updating the church’s air conditioning system, which has served us well for over 60 years. This is a large project, costing over $200,000. Most of the work is complete, and we have just received an invoice covering the portion just completed for over $100,000. If you would like to contribute to this project, please note “Air Conditioning Fund” on your check. Or click the Donate button below to donate online. Your support will be much appreciated.




The following photos show the progress that has been made so far. We hope you all will continue to support this project.

 

Old A/C ice tank
We don’t have any good photos of what the old air conditioning tank looked like, but this one from 2014 shows the ice tank off to the left covered in its blue foam insulation and the chilled water circulation pipes covered in their asbestos insulation from the 1950s.

 

Asbestos abatement
Oct. 22, 2019: The asbestos abatement team is removing sections of chilled water pipe covered in asbestos insulation. The blue foam insulation has been removed from the old ice tank.

 

Old ice tank
Oct. 25, 2019: The asbestos abatement has been completed, and the old ice tank is ready for demolition and removal.

 

Interior of old ice tank
Oct. 25, 2019: The interior of the old ice tank shows the Dole plates hanging vertically in the tank with the piping that circulates the refrigerant through the plates, causing ice to form in the tank. Everything is rusty.

 

New concrete pad
Jan. 22, 2020: The old ice tank has been removed, along with a layer of old cork insulation between the old tank and the floor. The installers found that the floor was not level and built a concrete leveling pad for the base of the new tank.

 

Covering the stairs
Feb. 12, 2020: Old parts were removed and new parts brought in through the subbasement and its outside entrance on the southwest corner of the church building. Plywood was placed on the concrete stairs to facilitate the movement of the large steel plates up the stairs.

 

New ice tank bottom
Feb. 12, 2020: The bottom of the new ice tank has been welded together from multiple plates. It is set up on blocks to keep the welding heat off the concrete pad and to allow new foam insulation to later be inserted under the completed tank.

 

New ice tank half built
Feb. 16, 2020: The bottom half of the new ice tank has been assembled. The new tank is situated a little farther away from the south wall than the old one. The wooden cross braces between two of the support posts (the ones wrapped in yellow on the far side of the tank) had to be moved to clear the top of the new tank. The wrapping on the posts is there to keep any sparks from the welding gear from igniting the old wood posts and causing a fire.

 

New ice tank full height
Feb. 19, 2020: The upper half of the new ice tank has been assembled. The old tank was carbon steel which was subject to rusting and had to be scraped and painted inside with a new protective coating every twenty years. Although the rust-resistant stainless steel of the new tank was more expensive than carbon steel, it does not have to be coated, and so it was actually less expensive than the cost of a new carbon steel tank plus the cost of the first protective coating. And it should never need to be scraped and coated periodically like the old tank.

 

Ports for pipes
Feb. 19, 2020: The ports for the connections for the recirculating chilled water are installed on the far side of the new ice tank.

 

Leak testing
Feb. 21, 2020: The new ice tank was completely filled with water to test its integrity. Even after more than a week, there were no leaks. New foam insulation has been installed under the new tank, and the wooden blocks have been removed.

 

Refrigerant piping assembly
Mar. 20, 2020: Installers begin to assemble the piping that will circulate the refrigerant on the inside of the new ice tank.

 

Recirculating pipe assembly
Mar. 20, 2020: Installers work on the piping that will circulate the chilled water from the new ice tank to the air circulation system.

 

Copper and brass fittings
Mar. 20, 2020: A work table contains the numerous copper and brass fittings needed to assemble the piping systems.

 

Refrigerant piping assembly
Mar. 20, 2020: Installers work on assembling the piping that will go inside the new ice tank.

 

Refrigerant piping assembly
Mar. 22, 2020: While the installers have to work inside the tank to assemble some of the piping structures to assure proper sizing, most of the structures are removed until the new Dole plates can be installed.

 

New compressor
Mar. 22, 2020: Some of the chilled water piping is completed, and the new compressor is installed on a stand instead of on the floor, for easier servicing.

 

Refrigerant piping assembly
Mar. 22, 2020: A piping structure for the inside of the new ice tank is on supports to facilitate assembly.

 

Dole plates
Mar. 23, 2020: The new Dole plates rest on a slab of blue foam insulation, awaiting installation.

 

Chilled water recirculation piping
Mar. 25, 2020: The remainder of the chilled water circulation piping is completed, connecting the pipes from the tank to the existing pipes leading to the air circulation system.

 

New pump
Mar. 25, 2020: The new red water recirculating pump is installed with the new chilled water circulation piping.

 

Dole plates installed
Apr. 1, 2020: The new Dole plates and much of their associated piping structures are installed inside the new ice tank.

 

Dole plates installed
Apr. 1, 2020: The new Dole plates are installed. The refrigerant piping is still in progress.

 

Dole plates installed
Apr. 1, 2020: The new Dole plates are installed. The refrigerant piping is still in progress.

 

Compressor piped and wired
Apr. 1, 2020: The new compressor has been connected to the exterior cooling tower, and electrical wiring in metal conduit connecting the pumps and compressor to the controls on the control panel are installed.

 

Compressor piped and wired
Apr. 4, 2020: Another view of the new compressor and associated piping and wiring.

 

Refrigerant piping installed
Apr. 4, 2020: More of the refrigerant piping inside the ice tank has been completed.

 

Refrigerant piping installed
Apr. 4, 2020: The installers retained the old refrigerant piping structures to use as templates in constructing these new ones.

 

Chilled water piping
Apr. 4, 2020: Special unions are installed where the new copper chilled water circulation pipe meets the existing iron pipe to prevent corrosion due to dissimilar metals.

 

Apr. 8, 2020: In May 2019, the exterior cooling tower for the air conditioning system was refurbished. Here, the deteriorating timber base that was formerly supporting the tower has been replaced by a concrete pad.

 

Apr. 12, 2020: A new foam plastic board lid has been fitted to insulate the top of the ice tank.

 

Apr. 12, 2020: More piping has been added to the chilled water recirculating system.

 

Apr. 12, 2020: This board contains the controls for the automatic chemical treatment system which will prevent scaling from hard water in the cooling tower and pipes.

 

Apr. 12, 2020: Pressure testing gear is attached to the compressor to ensure correct operation of the refrigeration components.

 

April 15, 2020: All the piping has been reattached to the exterior cooling tower.

 

April 15, 2020: While the other air conditioning system work was being done, we had the fan motor replaced on the exterior cooling tower. For several seasons now, the motor has been noisy, indicating failing bearings. Here, the old motor and fan have been removed, awaiting installation of a new unit. The grille for the opening is in the background resting against the foundation.

 

April 15, 2020: The foam insulation lid on the ice tank is complete, but the insulation has not yet been applied to the sides of the tank.

 

April 15, 2020: Most of the electrical controls for the new air conditioning system are installed on the mounting board.

 

Apr. 19, 2020: The chilled water recirculation pipes have been insulated with non-asbestos plastic foam and a white protective covering.

 

Apr. 19, 2020: The chilled water recirculation pipes have been insulated with non-asbestos plastic foam and a white protective covering.

 

Apr. 19, 2020: The controls for the automatic chemical treatment system, which will prevent scaling from hard water in the cooling tower and pipes, have been completed, and the system is activated, as shown by the lit LED screen in the upper left hand corner of the board.

 

Apr. 19, 2020: The electrical controls for the new air conditioning system are nearly complete.

 

Apr. 20, 2020: An installer explains how the plastic foam insulation sheets have been installed on the sides of the new ice tank. The black rubber sheet on the lid will be used to seal off the lid around the edges.

 

Apr. 20, 2020: The new fan motor has been installed on the exterior cooling tower, reusing the existing fan blades.

 

Apr. 22, 2020: The foam lid has been sealed around the edges.

 

Apr. 24, 2020: The Albert Arno project manager reports that the system is now operating and making ice. They will continue testing the following week.

 

Apr. 30, 2020. After running the cooling during the Wednesday evening meeting, the system has already made some ice by 10:30 a.m. the next morning.